About 26,000 households in southern Prague remained without heating or hot water on the morning of Friday, November 27, 2026, after a main pipe failed in Krč, according to heating supplier Pražská teplárenská. The supplier expected crews to finish repairs that evening but said the timing was an estimate.

The outage affected parts of Prague 4 and Prague 12, including Sídliště Krč, Zálesí, Lhotka, Kamýk and Modřany. Technicians had already restored service to around 3,000 households in Nové Dvory by switching their supply to the Krč heating plant.

The pipe failed near the intersection of Zálesí and Štúrova streets, where construction crews had been working. Pražská teplárenská said the work had not previously disrupted service. The company said the pipe’s condition deteriorated suddenly overnight and that crews needed to act immediately to keep the system safe and prevent further damage ahead of colder weather.

Residents can check Pražská teplárenská’s outage map for the affected area and repair progress. The Prague 4 and Prague 12 district offices also posted updates on their websites.

Further reading